TASK NAME | % COMPLETE |
---|---|
MAIN BULIDING CIVIL & ELECTRICAL WORKS | 95.00% |
SUBSTATION BUILDING ELECTRICAL WORKS | 98.00% |
SUBSTATION BUILDING CIVIL WORKS | 98.00% |
HVAC MECHANICAL WORKS | 96.00% |
FIRE PROTECTION SYSTEM | 94.00% |
LIGHTNING PROTECTION & BUILDING EARTHING | 98.00% |
FURNITURE & INTERIOR WORKS | 74.00% |
OUTDOOR LIGHTING | 55.00% |
CANOPY CONSTRUCTION & MAIN GATE INSTALLATION | 70.00% |
MAIN BUILDING COOLING TOWER MECHANICAL & ELECTRICAL WORKS | 92.00% |
MECHANICAL CAR PARKING WORKS | 98.00% |
EXTERIOR BEAUTIFICATION & MURALS | 50.00% |
BUILDING MANAGEMENT SYSTEM | 85.00% |
WOODEN MOULDING BEAD FIXING FOR OFFICE DOOR AND WINDOWS | 60.00% |
NETWORKING, IT, CCTV SURVILLIANCE SYSTEM, SERVER SYSTEM, EPABX & PA SYSTEM | 45.00% |
SOLAR PANEL SYSTEM INSTALLATION WORKS | 30.00% |
SL. NO | TASK NAME | TARGET DATE |
---|---|---|
1 | Interconnection of cables between panel to cooling tower motor at roof top shall be completed by | 07.06.2019 |
2 | Flooring work in cafeteria shall be started by | 07.06.2019 |
3 | Internal electrification of the main building shall be completed by | 07.06.2019 |
4 | 2nd coat painting works shall be completed by | 07.06.2019 |
5 | Construction of 2 nos security Goomty shall be completed by | 07.06.2019 |
6 | Interconnection between cooling tower and AHUs floor wise shall be completed by | 07.06.2019 |
7 | Installation of fire pumps at ground floors shall be completed by | 07.06.2019 |
8 | Fixing of hose pipe with false ceiling shall be complete by | 07.06.2019 |
9 | Casting of front side outer periphery of the main building and VIP car parking area shall be completed by | 07.06.2019 |
10 | Construction of the Gas Chamber shall be completed by | 07.06.2019 |
11 | Fitting of dropper & diffuser of HVAC system and firefighting works at the rooms with interior decorations shall be completed by | 07.06.2019 |
12 | Reorientation of the doors of all AHU rooms to make swing outwards shall be started by | 07.06.2019 |
13 | Glass door installation work for cafeteria at 8th floor shall be started by | 07.06.2019 |
14 | Final installation and charging of UPS at ground floor UPS room shall be completed by | 07.06.2019 |
15 | Interconnection of sensor cables for fire detection at 1st and 2nd floor shall be completed by | 07.06.2019 |