Work Progress

Overall Progress Percentage Complete : 89.00 %

Project Overview as on 03.06.2019

TASK NAME % COMPLETE
MAIN BULIDING CIVIL & ELECTRICAL WORKS 95.00%
SUBSTATION BUILDING ELECTRICAL WORKS 98.00%
SUBSTATION BUILDING CIVIL WORKS 98.00%
HVAC MECHANICAL WORKS 96.00%
FIRE PROTECTION SYSTEM 94.00%
LIGHTNING PROTECTION & BUILDING EARTHING 98.00%
FURNITURE & INTERIOR WORKS 74.00%
OUTDOOR LIGHTING 55.00%
CANOPY CONSTRUCTION & MAIN GATE INSTALLATION 70.00%
MAIN BUILDING COOLING TOWER MECHANICAL & ELECTRICAL WORKS 92.00%
MECHANICAL CAR PARKING WORKS 98.00%
EXTERIOR BEAUTIFICATION & MURALS 50.00%
BUILDING MANAGEMENT SYSTEM 85.00%
WOODEN MOULDING BEAD FIXING FOR OFFICE DOOR AND WINDOWS 60.00%
NETWORKING, IT, CCTV SURVILLIANCE SYSTEM, SERVER SYSTEM, EPABX & PA SYSTEM 45.00%
SOLAR PANEL SYSTEM INSTALLATION WORKS 30.00%

Upcoming Tasks -7 Days

SL. NO TASK NAME TARGET DATE
1 Interconnection of cables between panel to cooling tower motor at roof top shall be completed by 07.06.2019
2 Flooring work in cafeteria shall be started by 07.06.2019
3 Internal electrification of the main building shall be completed by 07.06.2019
4 2nd coat painting works shall be completed by 07.06.2019
5 Construction of 2 nos security Goomty shall be completed by 07.06.2019
6 Interconnection between cooling tower and AHUs floor wise shall be completed by 07.06.2019
7 Installation of fire pumps at ground floors shall be completed by 07.06.2019
8 Fixing of hose pipe with false ceiling shall be complete by 07.06.2019
9 Casting of front side outer periphery of the main building and VIP car parking area shall be completed by 07.06.2019
10 Construction of the Gas Chamber shall be completed by 07.06.2019
11 Fitting of dropper & diffuser of HVAC system and firefighting works at the rooms with interior decorations shall be completed by 07.06.2019
12 Reorientation of the doors of all AHU rooms to make swing outwards shall be started by 07.06.2019
13 Glass door installation work for cafeteria at 8th floor shall be started by 07.06.2019
14 Final installation and charging of UPS at ground floor UPS room shall be completed by 07.06.2019
15 Interconnection of sensor cables for fire detection at 1st and 2nd floor shall be completed by 07.06.2019