| TASK NAME | % COMPLETE |
|---|---|
| MAIN BULIDING CIVIL & ELECTRICAL WORKS | 95.00% |
| SUBSTATION BUILDING ELECTRICAL WORKS | 98.00% |
| SUBSTATION BUILDING CIVIL WORKS | 98.00% |
| HVAC MECHANICAL WORKS | 96.00% |
| FIRE PROTECTION SYSTEM | 94.00% |
| LIGHTNING PROTECTION & BUILDING EARTHING | 98.00% |
| FURNITURE & INTERIOR WORKS | 74.00% |
| OUTDOOR LIGHTING | 55.00% |
| CANOPY CONSTRUCTION & MAIN GATE INSTALLATION | 70.00% |
| MAIN BUILDING COOLING TOWER MECHANICAL & ELECTRICAL WORKS | 92.00% |
| MECHANICAL CAR PARKING WORKS | 98.00% |
| EXTERIOR BEAUTIFICATION & MURALS | 50.00% |
| BUILDING MANAGEMENT SYSTEM | 85.00% |
| WOODEN MOULDING BEAD FIXING FOR OFFICE DOOR AND WINDOWS | 60.00% |
| NETWORKING, IT, CCTV SURVILLIANCE SYSTEM, SERVER SYSTEM, EPABX & PA SYSTEM | 45.00% |
| SOLAR PANEL SYSTEM INSTALLATION WORKS | 30.00% |
| SL. NO | TASK NAME | TARGET DATE |
|---|---|---|
| 1 | Interconnection of cables between panel to cooling tower motor at roof top shall be completed by | 07.06.2019 |
| 2 | Flooring work in cafeteria shall be started by | 07.06.2019 |
| 3 | Internal electrification of the main building shall be completed by | 07.06.2019 |
| 4 | 2nd coat painting works shall be completed by | 07.06.2019 |
| 5 | Construction of 2 nos security Goomty shall be completed by | 07.06.2019 |
| 6 | Interconnection between cooling tower and AHUs floor wise shall be completed by | 07.06.2019 |
| 7 | Installation of fire pumps at ground floors shall be completed by | 07.06.2019 |
| 8 | Fixing of hose pipe with false ceiling shall be complete by | 07.06.2019 |
| 9 | Casting of front side outer periphery of the main building and VIP car parking area shall be completed by | 07.06.2019 |
| 10 | Construction of the Gas Chamber shall be completed by | 07.06.2019 |
| 11 | Fitting of dropper & diffuser of HVAC system and firefighting works at the rooms with interior decorations shall be completed by | 07.06.2019 |
| 12 | Reorientation of the doors of all AHU rooms to make swing outwards shall be started by | 07.06.2019 |
| 13 | Glass door installation work for cafeteria at 8th floor shall be started by | 07.06.2019 |
| 14 | Final installation and charging of UPS at ground floor UPS room shall be completed by | 07.06.2019 |
| 15 | Interconnection of sensor cables for fire detection at 1st and 2nd floor shall be completed by | 07.06.2019 |