Work Progress

Overall Progress Percentage Complete : 85.00%

Project Overview as on 16.03.2019

TASK NAME % COMPLETE
MAIN BULIDING CIVIL & ELECTRICAL WORKS 88.00%
SUBSTATION BUILDING CIVIL & ELECTRICAL WORKS 90.00%
HVAC MECHANICAL WORKS 85.00%
FIRE PROTECTION SYSTEM 85.00%
BUILDING MANAGEMENT SYSTEM 75.00%
LIGHTNING PROTECTION & BUILDING EARTHING 95.00%
MECHANICAL CAR PARKING WORKS 70.00%
FURNITURE & INTERIOR WORKS 50.00%
NETWORKING, IT, CCTV SURVILLIANCE SYSTEM, SERVER SYSTEM, EPABX & PA SYSTEM 40.00%

Upcoming Tasks -7 Days

SL. NO TASK NAME TARGET DATE
1 Fitting and fixing of balance number of glasses for structural glazing 16.03.2019
2 Fitting and fixing of balance number of glasses for structural glazing 16.03.2019
3 Fitting of Kitchen tiles 17.03.2019
4 Fitting and fixing of balance number of glasses for structural glazing 16.03.2019
5 Internal painting after application of putty & primer at 2nd floor 16.03.2019
6 Internal painting over walls & ceilings of stairs at eastern and western sides of the main building 16.03.2019
7 Glass door installation work for cafeteria at 8th floor 16.03.2019
8 Casting of front side outer periphery of the main building 16.03.2019
9 Casting of front side outer periphery of the main building 16.03.2019
10 Dismantling of existing front side boundary wall (partly) shall be completed by and new construction 16.03.2019
11 Fitting of toilet accessories at 1st floor 16.03.2019
12 Installation of balance of number of paver blocks 16.03.2019
13 Internal electrification of the main building 16.03.2019
14 Installation of lighting arrestor at roof top of the main building 16.03.2019
15 Interconnection between cooling tower and AHUs in 5th floor 16.03.2019
16 Installation of AHU DBs floor wise 16.03.2019
17 Interconnection of cables between fire detection floor wise and fire panel at ground floor 16.03.2019
18 Earthing of lift control panels at lift machine room 16.03.2019
19 Fitting of dropper & diffuser of HVAC system at 2nd floor 16.03.2019
20 Internal electrical wiring in Substation Building 16.03.2019
21 Framing of false ceiling for the rooms under Interior’s scope 16.03.2019
22 Making of furniture for 1st, 3rd 4th, 6th and 7th floor 16.03.2019
23 Installation of bead board paneling for office windows, doors & columns at 3rd floor 16.03.2019
24 Casting of foundation footing at mechanical car parking area 16.03.2019