Work Progress

Overall Progress Percentage Complete : 88.00 %

Project Overview as on 27.04.2019

TASK NAME % COMPLETE
MAIN BULIDING CIVIL & ELECTRICAL WORKS 95.00%
SUBSTATION BUILDING CIVIL WORKS 95.00%
SUBSTATION BUILDING ELECTRICAL WORKS 95.00%
HVAC MECHANICAL WORKS 90.00%
FIRE PROTECTION SYSTEM 85.00%
BUILDING MANAGEMENT SYSTEM 80.00%
LIGHTNING PROTECTION & BUILDING EARTHING 98.00%
MECHANICAL CAR PARKING WORKS 85.00%
MAIN BUILDING COOLING TOWER MECHANICAL & ELECTRICAL WORKS 85.00%
SOLAR PANEL SYSTEM INSTALLATION WORKS 30.00%
NETWORKING, IT, CCTV SURVILLIANCE SYSTEM, SERVER SYSTEM, EPABX & PA SYSTEM 45.00%
FURNITURE & INTERIOR WORKS 55.00%
OUTDOOR LIGHTING 50.00%
EXTERIOR BEAUTIFICATION & MURALS 50.00%
CANOPY CONSTRUCTION & MAIN GATE INSTALLATION 60.00%
WOODEN MOULDING BEAD FIXING FOR OFFICE DOOR AND WINDOWS 40.00%

Upcoming Tasks -7 Days

SL. NO TASK NAME TARGET DATE
1 Flooring work in cafeteria shall be started by 03.05.2019
2 Existing entrance of Canteen shall be blocked and cutting of newly located door shall be started by 03.05.2019
3 Internal electrification of the main building shall be completed by 03.05.2019
4 Internal electrical wiring of substation building shall be completed by 03.05.2019
5 Fitting of dropper & diffuser of HVAC system and firefighting works at the rooms with interior decorations shall be completed by 03.05.2019
6 Glass door installation work for cafeteria at 8th floor shall be started by 03.05.2019
7 Installation AHU DBs at AHU rooms shall be started by 03.05.2019
8 Painting of false celling shall be completed by 03.05.2019
9 Laying of cooling tower MS pipe at roof top 03.05.2019
10 Installation of bead board paneling for office windows, doors & columns at 1st, 2nd , 3rd , 4th , 5th floor shall be completed by 03.05.2019
11 Outside border painting of Substation Building shall be completed by 03.05.2019
12 Fitting and fixing of Granites over the front boundary at eastern side of the main building shall be started by 03.05.2019
13 Construction of Pantry at cafeteria shall be started by 03.05.2019
14 Leveling of 4 nos slab over UGR at Southern side of the main building shall be completed by 03.05.2019
15 Interconnection of cables between fire detection panel at ground floor and various sensors floor wise shall be completed by 03.05.2019
16 Existing door of the Police room shall be blocked and cutting of newly located door shall be started by 03.05.2019
17 Fixing of granites on the outer wall of northern side of the main building shall be completed by 03.05.2019
18 2nd coat painting works shall be completed by 03.05.2019
19 Construction of beam at main gates shall be started by 03.05.2019
20 Fitting and fixing of glasses at substation building shall be started by 03.05.2019
21 Construction of the Gas Chamber shall be completed by 03.05.2019
22 Covering up of 4 nos main cable shafts at each floor shall be completed by 03.05.2019
23 Interconnection between cooling tower and AHUs floor wise shall be completed by 03.05.2019
24 Power line coordination with various loads shall be complete by 03.05.2019
25 Structural works at western side at within building mechanical car parking area shall be completed by 03.05.2019
26 Finishing work over the outdoor cable trench shall be completed by 03.05.2019
27 Construction of 2 nos security Goomty shall be completed by 03.05.2019
28 Casting of front side outer periphery of the main building shall be completed by 03.05.2019
29 Installation of Cooling Tower panels at roof top shall be completed by 03.05.2019
30 Fitting and fixing of balance number calcium silicate boards for false ceiling shall be completed by 03.05.2019
31 Making of furniture and false ceiling works for 4th, 5th , 6th and 7th floor 03.05.2019
32 Reorientation of the doors of all AHU rooms to make swing outwards shall be started by 03.05.2019